A Pittsburgh remodel can involve two permitting systems. The City handles building and several trades; Allegheny County handles plumbing. Keep the applications, approvals, and inspection records coordinated so one missing record does not hold up the next stage.

Official sources checked October 2, 2026. The workflow below is an organizing method; your approved scope and the reviewing agencies determine the requirements for your project.

1. Separate the authorities before filing

Pittsburgh PLI issues separate permits for building work and systems such as electrical, mechanical, fire alarm, and suppression. Plumbing permits are handled by the Allegheny County Health Department (ACHD). A city permit is not a substitute for county plumbing approval. PLI permit types

  • City work: list the building and trade scopes you need to confirm with PLI.
  • Plumbing: give the plumber the same scope and drawing revision used by the city team.
  • Address: confirm the municipality first. This city workflow applies inside Pittsburgh; an address elsewhere in Allegheny County needs its own municipal building-permit check.

Check the City’s work not requiring a permit before selecting an application. Ask PLI about uncertain scopes rather than labeling the entire remodel exempt because one task is cosmetic.

2. Build a shared scope record

For a remodel that moves a sink, alters walls, and changes circuits, write three separate scope lines. Give each line an owner, a drawing reference, an agency, and a next action. This example organizes the questions; it does not decide which permits your specific building needs.

Building scope
Identify walls being removed or added, existing and proposed use, and the plan sheet showing each change. Assign the city application and any zoning questions to one coordinator.
Electrical and mechanical scopes
Record circuit, equipment, and ventilation changes separately. Ask each trade contractor to confirm its application and inspection responsibilities.
Plumbing scope
Record the fixtures being installed or altered and the related drawing revision. Assign county review and inspection follow-up to the plumbing lead.

Keep one revision log: date, changed scope, changed sheets, agencies notified, and response received. An email saying “updated plans attached” is harder to reconcile than a record identifying exactly which sheet and fixture changed.

3. Prepare the county plumbing package

ACHD’s guidance calls for a plumbing plan covering installed or altered fixtures, water service, building sewers, and a drawing of locations, connections, and materials. Plans and permits can be filed through its Citizen Access Portal. Commercial projects need commercial plan-review approval before filing the commercial plumbing plan. Obtain the required plan approval and permit before starting plumbing work. ACHD filing guidance

For commercial work, use the county’s Commercial Plan Review Checklist (PDF) to identify scope-specific items. It covers building classification, occupancy, fixture needs, and sewer information, among other topics. Review applicable items with the plumbing designer instead of treating a generic checklist as the full submission standard.

4. Record issuance separately from review approval

PLI’s issuance guidance separates plan approval from permit issuance. Conditions, applicable licenses, contractor assignment, and outstanding fees can remain after review. Work is authorized after issuance for the scope covered by that permit. A scope or design change may require an amendment. City issuance requirements

In your project record, use distinct statuses: submitted, corrections requested, approved, issued, inspections pending, and complete. Save the actual issuance document beside the approved drawing revision. Release each trade to work only after its required authorization is confirmed.

5. Make inspection records part of the handoff

PLI requires approved documents on site and work to remain exposed until a passed inspection authorizes concealment. Its sequencing guidance requires passed sub-permit inspections for framing and calls for the ACHD plumbing inspection report as a close-out document. The city permit holder requests PLI inspections through OneStopPGH. PLI inspection sequencing

Keep the county inspection report with the related city record. ACHD also requires a final inspection for its plumbing permits. County inspection requirement

  • Before scheduling closure or framing, ask each trade for its required inspection outcome.
  • Save the report, inspection date, permit number, and any correction still open.
  • Assign an owner to request the next inspection and resolve missing documents.
  • At handoff, reconcile every permit against its completion requirements rather than assuming one final inspection closes the entire remodel.

A compact record your team can reuse

Create one row per permit or review with these fields:

Address and municipality · scope · agency · responsible contractor · application/permit number · current status · approved drawing revision · inspection result/report · next action and owner

This makes the city/county handoff visible to the general contractor, plumber, designer, and owner. Use our Pittsburgh plumbing guide and Pittsburgh permit checker to organize early questions, then confirm requirements against the official sources and project approvals.