City GuideAlbuquerque, NMOfficial resources checked 2026-10-12

Albuquerque Contractor Licensing & Permit Guide (2026)

Submit through ABQ-PLAN, distinguish standard and Fas Trax review, and respect licensed-trade restrictions.

The skyline of downtown Albuquerque, New Mexico. The city is home to 564,000 residents and is the 32nd most populous city in the U.S.
Photo: Quintin Soloviev · CC BY 4.0 · Resized for this guide.

Confirm current licensing, code editions, fees and project requirements with the issuing department before starting work.

Overview

Albuquerque Building Safety coordinates City construction permits. ABQ-PLAN accepts plans and supporting material. Confirm City jurisdiction and the full scope before selecting standard or optional expedited review.

Online submission

ABQ-PLAN applications and supporting documents

Standard review component

65% of permit fee, plus zoning and hydrology

Trades

Select a trade for its permit path, licensing, code resources, fees and filing pitfalls.

Electrical additions and replacements

Albuquerque Building Safety

Applicable Code

Applicable New Mexico and City electrical requirements.

License Requirement

Verify New Mexico electrical contractor scope and any owner authorization.

License Fee

New Mexico RLD credential assessment

CEUs

Check electrical renewal obligations

Permit Fee

Current electrical fee not verified; excluded from the worked example. Obtain the scope-specific electrical assessment; the review example is not an electrical flat fee.

Plan Review Time

Declare appliances, wiring and service-amperage changes.

Common Pitfalls

  • Replacement work can require permits and inspections.
  • A building permit does not authorize undeclared electrical alterations.

Permit-to-closeout workflow

01

Confirm authority

City property and complete building/trade scope

02

Prepare plans

Drawings and supporting agency documents

03

Submit ABQ-PLAN

Complete application and review payment

04

Resolve divisions

Building and required zoning/hydrology/agency comments

05

Issue and inspect

Correct permit holder schedules construction stages

06

Complete finals

Resolve corrections and applicable occupancy documentation

Permit fees and worked estimates

The actual City FAQ supplies percentages, not a universal dollar base. The linked detailed fee document was inaccessible; no tariff was inferred from it.

Conditional example, checked October 12, 2026: assume an assessed building permit fee of $1,000. Standard review component = $1,000 × 65% = $650; Fas Trax review component = $650 × 3 = $1,950. The $1,000 is assumed, not an official flat rate. Zoning, hydrology, issuance, trades and other charges are excluded; do not add standard and Fas Trax as two separate review charges.
TradePermit feeLicense fee
Electrical additions and replacementsCurrent electrical fee not verified; excluded from the worked example. Obtain the scope-specific electrical assessment; the review example is not an electrical flat fee.New Mexico RLD credential assessment
Water heaters, piping and servicesCurrent plumbing fee not verified; excluded from the worked example. Plumbing fees depend on installations; standard building-review formula is not a fixture tariff.RLD specialty credential schedule
Equipment, ducts and hoodsCurrent mechanical fee not verified; excluded from the worked example. Obtain mechanical scope fees and related review assessment.RLD specialty schedule
Fire-system coordinationCurrent fire fee not verified; excluded from the worked example. Fire and other division assessments are separate from the conditional review example.System-specific credential assessment
Standard review and Fas TraxStandard review is 65% of permit fee plus zoning/hydrology; Fas Trax review is three times the standard review component excluding those fees.RLD credential schedule

Submission checklist

Address, proposed use and complete project scope.
Building and discipline drawings and supporting calculations.
Required zoning, hydrology and other division documentation.
Contractor credentials or approved homeowner application information.

Homeowner and codes

A homeowner construction route exists, but City trade guidance imposes specific licensed-contractor restrictions for water heaters and equipment/duct installations. Use the current City code links and scope requirements; an owner application does not establish every trade exemption.

Inspections and closeout

The permit holder schedules inspections; contractor-held permits should be scheduled by the contractor. Requests before 4: 15 p.m. are generally next business day, with no fixed visit time. Keep plans on site and complete the applicable finals; the residential inspection page scopes occupancy certificates to new homes.

Official resources

Albuquerque building permit guide | PermitOps