Overview
BSEED’s current building-permit page directs applicants to Accela/eLAPS. Submit the application and required fee, then respond to customer-service review and upload requested documents. Follow correction emails and check the portal. Water/sewer approvals are separately handled by DWSD and right-of-way work by DPW.
Authority
Buildings, Safety Engineering and Environmental Department (BSEED)
Portal
Accela / eLAPS
Trades
Select a trade for its permit path, licensing, code resources, fees and filing pitfalls.
Electrical scope and permit coordination
Detroit BSEED / applicable Michigan authorityApplicable Code
Confirm the City electrical provisions and filing-date state code.
License Requirement
Specific current contractor registration and owner-work eligibility not verified; confirm before applying.
License Fee
Current credential and registration amounts not verified in this review.
CEUs
Current credential-specific renewal hours not verified here.
Permit Fee
Current electrical permit rate not verified; excluded from the historical refund illustration.
Plan Review Time
Confirm the selected trade service and required document review in eLAPS.
Common Pitfalls
- A building application does not establish electrical contractor eligibility.
- A paid intake fee does not replace the issued permit and required inspections.
Permit-to-closeout workflow
Define jurisdiction and scope
Confirm Detroit property and required building, trade and external approvals.
Create eLAPS account
Submit the selected application and required intake fee.
Upload complete records
Respond to the customer-service review and provide requested plans/specifications.
Resolve corrections
Monitor email notifications and the Accela record.
Obtain and post permits
Download issued records and post permits on the property exterior.
Inspect and certify
Complete required construction inspections and acceptance/occupancy records.
Permit fees and worked estimates
The City currently offers a schedule labeled effective January 1, 2024, modified July 18, 2025. Its actual PDF body could not be read here, so current permit and trade rates remain unverified.
| Trade | Permit fee | License fee |
|---|---|---|
| Electrical scope and permit coordination | Current electrical permit rate not verified; excluded from the historical refund illustration. | Current credential and registration amounts not verified in this review. |
| Plumbing and water-service coordination | Current plumbing permit rate not verified; excluded from the historical refund illustration. | Current credential and registration amounts not verified in this review. |
| Mechanical permit and plan scope | Current mechanical permit rate not verified; excluded from the historical refund illustration. | Current credential and registration amounts not verified in this review. |
| Fire and system approval coordination | Current fire/system permit rate not verified; excluded from the historical refund illustration. | Current specialist and registration amounts not verified in this review. |
| Building permit and construction closeout | Current building permit rate not verified. Archived August 2021 text illustrates an 80% conditional refund, not a current permit price. This unverified amount is excluded from the worked example. | Current contractor credential and registration amounts not verified in this review. |
Submission checklist
Homeowner and licensing
Confirm the applicant, contractor credentials and any owner-work exception with BSEED for each discipline. This review did not establish a current broad homeowner exemption or license-price table. Ownership alone should not be treated as approval to perform regulated trade work.
Codes and amendments
Confirm current state-code applicability and Detroit additions for the filing date. The retrieved Municode version is explicitly an August 18, 2021 archive; its older code-edition references and refund provision are not presented as current adoption or current fees.
Inspections and closeout
The current City process requires construction inspections and directs scheduling questions to its construction-inspection guidance. After completion, obtain a Certificate of Acceptance and/or Certificate of Occupancy; some projects require both. Keep approved records available and confirm the actual stage sequence before covering work.