Overview

City of Orlando Permitting Services handles City construction applications. Confirm City boundaries before using these instructions; Orange County permitting is a separate route.

Permit authority

City Permitting Services; separate from Orange County

Code cycle

2023 Florida Building Code / 2020 NEC

Trades

Select a trade for its permit path, licensing, code resources, fees and filing pitfalls.

Electrical installations and service changes

Orlando Permitting / DBPR

Applicable Code

2020 NEC and 2023 Florida energy provisions.

License Requirement

Florida electrical contractor category appropriate to the work; keep contractor documents current with the City.

License Fee

DBPR electrical schedule

CEUs

DBPR category-specific renewal

Permit Fee

January 2023 residential schedule: $63.67 first $1,000; $10.60 each additional $1,000 or fraction through $25,000; surcharges extra. Confirm current assessment.

Plan Review Time

Digital review requirements depend on the electrical scope.

Common Pitfalls

  • Do not substitute an Orange County application for a City property.
  • Building approval does not cover every trade permit.

Permit-to-closeout workflow

01

Confirm the property and project

Use City jurisdiction and select the relevant residential or commercial checklist.

02

Prepare forms and drawings

Include site information, required signatures and current contractor documents.

03

Apply and upload plans

Follow the City application instructions and digital plan-review invitation.

04

Resolve review and fees

Respond to comments and obtain all issued building/trade permits.

05

Record documents and inspect

Submit and post the NOC where required; arrange inspections through the City tools.

06

Finish and close out

Clear inspection corrections and confirm the required completion/use approval.

Permit fees and worked estimates

The retrieved City residential schedule is explicitly effective January 2023 and printed May 22, 2023. It is a dated planning example, not a verified 2026 fee quote. Obtain the current City assessment before budgeting a final amount.

Assume a $3,000 residential electrical scope under the January 2023 table: $63.67 + 2 × $10.60 = $84.87. Add 3% technology ($2.55), 1.5% inspection fund ($2 minimum) and 1% operational fund ($2 minimum): $91.42 subtotal after component rounding. Excludes other permit types, service-change charges, utility/impact charges and revisions.
TradePermit feeLicense fee
Electrical installations and service changesJanuary 2023 residential schedule: $63.67 first $1,000; $10.60 each additional $1,000 or fraction through $25,000; surcharges extra. Confirm current assessment.DBPR electrical schedule
Residential plumbing and gasJanuary 2023 residential schedule: $60 + $7 per fixture, before surcharges; three fixtures = $81 permit component. Confirm current invoice.DBPR construction schedule
HVAC equipment and ventilationJanuary 2023 residential schedule: $64.94 first $1,000 plus $10.81 each additional $1,000 or fraction through $25,000. Current charges require confirmation.DBPR category-specific schedule
Alarms and suppression systemsJanuary 2023 residential table: $64.94 first $1,000 + $8.66 each additional $1,000 through $25,000 for alarm/suppression; confirm present scope and charges.System licensing authority schedule
Construction, additions and owner applicationsJanuary 2023 residential schedule lists a $150 reinspection component and a 3% technology surcharge; use the project’s building valuation category for its main fee.DBPR firm and qualifier schedule

Codes and amendments

The City’s code page applies the 2023 eighth-edition Florida volumes and 2020 NEC to applications submitted after December 30, 2023. It also identifies Florida-amended NFPA 1/101 and municipal engineering and development standards.

Submission checklist

Use the checklist for the actual project type.
Include required site/survey information and dimensioned plans.
Confirm signed/sealed documents where the checklist requires them.
File current license, business-tax and insurance documents; registered contractors have additional bond/card requirements.
Include owner-builder and NOC documents when applicable.

Homeowner rules

Residential owner-managed applications need an Owner/Builder Declaration and sometimes a recorded NOC. The declaration establishes owner responsibilities; it is not a blanket exemption from trade permits or inspection. Use the project checklist for signature and in-person requirements.

Enforcement and revisions

The residential checklist explains how to identify changes, submit the revised sheets and respond to comments. Work beyond the issued scope needs the appropriate approval; address corrections before arranging final inspections.

Inspections and closeout

The City supports inspection scheduling online, by text or phone. For a permit requiring a recorded NOC, record it with the Orange County Comptroller, submit it to the City and post the certified copy at the job site. Clear all required inspection stages and confirm completion/use documentation.