Seattle Contractor Licensing & Permit Guide (2026)

Research Seattle properties, prepare SDCI submissions and use the Seattle Services Portal.

City view of Seattle
Photo: Jeffery Hayes · CC BY-SA 3.0 · Resized for this guide.

Confirm current licensing, code editions, fees and project requirements with the issuing department before starting work.

Overview

Seattle Department of Construction and Inspections (SDCI) manages city construction and land-use permitting. Establish that the property is within Seattle; other King County jurisdictions use their own services.

Main portal

Seattle Services Portal

Construction intake

Building and Land Use Pre-Application first

Trades

Select a trade for its permit path, licensing, code resources, fees and filing pitfalls.

Seattle electrical installations

Seattle SDCI

Applicable Code

Seattle Electrical Code; use SDCI’s current permit and code-change resources.

License Requirement

Washington L&I electrical contractor license is distinct from general contractor registration; homeowner eligibility must be checked for the work.

License Fee

L&I electrical contractor licensing schedule

CEUs

L&I electrical certification and renewal education rules

Permit Fee

2026 no-plan 150–200A service: $292 + $55.48 administration; with 5% technology fee, $364.85. Circuit/equipment or reviewed-plan fees may be additional.

Plan Review Time

Seattle distinguishes over-the-counter electrical permits from installations requiring review.

Common Pitfalls

  • General contractor registration alone does not authorize electrical contracting.
  • Keep rough wiring exposed until SDCI approves the required inspection.

Permit-to-closeout workflow

01

Research property

Review zoning, permit history and planned use

02

Pre-apply

Submit the preliminary site plan and receive assessment requirements

03

Prepare intake

Complete SDCI forms, drawings and electronic intake submission

04

Coordinate agencies

Separate plumbing/gas, electrical and fire-system approvals

05

Inspect work

Complete construction, trade and system acceptance inspections

06

Obtain finals

Resolve corrections and required occupancy approval

Permit fees and worked estimates

Seattle’s 2026 Fee Subtitle uses a $292 base/hourly rate and a 5% technology charge on listed SDCI fees. The Development Fee Index (DFI) is $325 for the first $1,000 plus $1.60 per additional $100 or fraction through $25,000. Standard building permit and review each use 100% of DFI; qualifying STFI uses 100% permit plus 40% review. Plumbing is a separate Public Health fee schedule effective January 1, 2026.

$10,000 standard building project: DFI = $325 + 90 × $1.60 = $469. Permit $469 + review $469 + technology $46.90 = estimated $984.90 subtotal. Excludes land-use/site, utility, separate trade and other agency charges.
$10,000 qualifying STFI project: $469 permit + $187.60 review + $32.83 technology = $689.43 subtotal. Eligibility is required; site, land-use and separate trade charges are excluded.
One no-plan 150–200A electrical service: ($292 + $55.48) × 1.05 = $364.85. Extra circuits/equipment and Seattle City Light charges are not included.
Three plumbing fixtures: $137 + 3 × $27 = $218 Public Health permit. Excludes $273/hour review when needed, repipe supplements, $137 reinspections and other system permits.
TradePermit feeLicense fee
Seattle electrical installations2026 no-plan 150–200A service: $292 + $55.48 administration; with 5% technology fee, $364.85. Circuit/equipment or reviewed-plan fees may be additional.L&I electrical contractor licensing schedule
Plumbing, gas piping and backflow2026 Public Health: $137 base + $27 per fixture/outlet. Three plumbing fixtures = $218 permit; plan review at $273/hour and repipe inspection supplements are additional.L&I plumbing contractor schedule and separate required bond
Mechanical and ventilation work2026 no-plan furnace/heat pump: $60.35 per unit; with 5% technology fee, $63.37. Refrigeration, electrical and gas approvals are separate.L&I contractor registration schedule; equipment credentials may be separate
Fire alarms, sprinklers and acceptance2026 no-plan alarm electrical component: $17.52 per control unit + $2.92 per device, $55.48 administration; standard OTC minimum $105.12. Seattle Fire services are additional.State trade credentials and applicable SFD certification schedule
Construction and land-use coordination2026 full-review building fee = 100% Development Fee Index permit + 100% index review + 5% technology. $10,000 valuation example: $984.90 subtotal before other reviews.L&I lists a $150.20 contractor registration application fee; bond and insurance are additional.

Who handles the trade approvals?

Seattle plumbing and gas piping permits and inspections run through Public Health — Seattle & King County. SDCI administers electrical and mechanical construction permits. Fire alarm approvals involve both SDCI and Seattle Fire. Check each agency’s final requirements rather than treating one construction record as approval for every system.

Choose your permit route

Use SDCI’s permit-type guidance for new construction, alterations, trade work or land-use approvals. Most applications go through the Seattle Services Portal. Construction and land-use applications start with a Building and Land Use Pre-Application, including projects using the Subject-to-Field-Inspection route.

Submission checklist

Research property zoning, permit history and the proposed use.
Prepare the preliminary site plan required for the pre-application.
Use the relevant SDCI forms, checklists and plan-drawing standards.
Address requirements in the preliminary assessment and identify related agency approvals.

Application and review

Create a Seattle Services Portal account. After the preliminary assessment, prepare the complete submission and follow the electronic intake instructions. Answer review comments and obtain the issued permit before proceeding with permitted work.

Codes and Seattle amendments

SDCI’s building-code page identifies the 2021 IBC with Seattle amendments and provides the Seattle Building Code with errata. It directs qualifying houses, duplexes and townhouses to the separate Residential Code. Check the relevant energy, trade and existing-building code resources for the project.

Inspections and closeout

Schedule the permit’s required construction inspections through the City’s inspection resources. Arrange separate trade, fire or special inspections where required. Complete corrections and final approvals, including occupancy approval when applicable.